Project Spotlight: Can Manufacturing Facility – Golden, Colorado
Our team partnered with a major can manufacturing facility in Golden, Colorado, on a multi-year roof restoration and protection program across several buildings within the complex. This high-demand industrial environment requires durable solutions, meticulous planning, and strict compliance with sanitation and safety standards. Using the AG PUMA system, we have successfully restored and protected tens of thousands of square feet of roofing and continue to work with the client to address additional areas as their budget allows.
Year 1 – Foundation of the Restoration Plan
Total Year 1 Area Completed: 17,796 sq. ft.
The first year focused on the most critical and heavily impacted areas across Buildings 21, 20 West, and 20 East. Our scope included complete cleaning, surface preparation, priming, and installation of the AG PUMA Base Coat and Top Coat system.
Core Scope of Work:
- Power washing to remove contaminants, oils, and debris
- Pumping collected water to the sanitary sewer per facility requirements
- Concrete repair using AG PUMA THIX
- Priming with AG PUMA Primer 107
- Installing AG PUMA Base Coat
- Installing AG PUMA Light Grey Top Coat with back-rolled anti-slip aggregate
Building 21 – 5,446 sq. ft.
Included grease-contaminated areas, ponding zones, TPO containment sections, and restoration around multiple AHUs.
Building 20 West – 8,170 sq. ft.
Focused on exhaust areas, chemical-exposed roof sections, and elevated platforms.
Building 20 East – 4,180 sq. ft.
Included silicone patch replacements, penetration reinforcement, curb repairs, and work where old containment structures had been removed.
Year 2 – Continued System Expansion
Total Year 2 Area Completed: 18,811 sq. ft.
In Year 2, we expanded coverage across Buildings 20 East and 20 West while also removing loose or delaminated flashings and completing additional surface repairs.
Scope of Work:
- Complete cleaning and surface preparation
- Water management to sanitary sewer
- Removal of loose or delaminated flashings
- Concrete patching with AG PUMA THIX
- Primer, base coat, and top coat installation
Building 20 East – 4,512 sq. ft.
Building 20 West – 14,299 sq. ft.
Year 3 – Ongoing Restoration Efforts
Total Year 3 Area Completed: 16,243 sq. ft.
Work in Year 3 continued the systematic restoration of Building 20 East. The installation process remained consistent to ensure seamless integration with prior years and long-term performance.
Scope of Work:
- Roof cleaning and power washing
- Water removal and pumping per facility standards
- Removal of loose or delaminated flashings
- Concrete repairs with AG PUMA THIX
- AG PUMA Primer, Base Coat, and Light Grey Top Coat installation with anti-slip aggregate
Building 20 East – 16,243 sq. ft.
Ongoing Commitment
While significant progress has been made, this project is still active. We continue to partner with the client to prioritize and address additional roof sections—totaling thousands of remaining square feet—as their annual budget allows. This phased approach ensures they receive high-quality, long-lasting roofing solutions without disrupting operations or exceeding capital planning constraints.